A Planning Application for RED III development should be made on the Council’s Planning Application Form.
Below provides a summary of the applicable timelines upon receipt of confirmation of a complete application:
- Development Type: Renewable energy development with an electrical capacity of 150kW or more
Deadline for Decision: 52 weeks
Extended deadline for IROPI Cases: 2 years
- Development Type: Renewable energy development with capacity of less than 150kW and repowering development
Deadline for Decision: 30 weeks
Extended deadline for IROPI Cases: 1 year
- Development Type: Ground source heat pumps and relevant solar energy development
Deadline for Decision: 8 weeks
Extended deadline for IROPI Cases: N/A
- Development Type: Small-scale solar energy equipment or small-scale non-ground source heat pump
Deadline for Decision: 4 weeks
Extended deadline for IROPI Cases: N/A
- Development Type: Offshore renewable energy development with an electrical capacity of 150kW or more
Deadline for Decision: 65 weeks
Extended deadline for IROPI Cases: 3 years
- Development Type: Offshore renewable energy development with an electrical capacity of less than 150kW or repowering development
Deadline for Decision: 52 weeks
Extended deadline for IROPI Cases: 2 years
Timelines for decision-making cannot be paused because of requests for further information or due to the requirement to carry out an environmental assessment. For these reasons, the Department of Housing, Local Government and Heritage issued a circular on 15 August 2025 advising that a policy decision had been made to disapply further information requests for certain developments captured by the Regulations. These developments are relevant solar energy development, small-scale solar energy equipment developments and heat pumps. However, it remains possible to request further information for certain other renewable energy developments subject to the Regulations. In these circumstances, the planning authority must issue a request for further information within 8 weeks of the date of a completeness check notice being given and the planning authority must specify the period for replying to such a request. Where an applicant does not provide the information within the period specified, the application shall be considered as withdrawn.